Vista de página 4
Site requirements 5
You have chilled water at your final location.
You have made provisions for properly grounding the HP POD.
System utilities
Your site location must accommodate the following utilities:
Cooling water
Electrical power ("Power" on page 5)
Drainage (on page 6)
Power
Item Description
1 Main input power junction box
2 Chilled water return connection
3 Chilled water supply connection
4 IT cable portals