IST-2000-25187
Deliverable D4.3
Evaluation of Phase I Field Trial
TORRENT
IST-2000-25187 PUBLIC Page 6 of 77
1 Introduction
The first deliverable of this WP, D4.1 “Metrics for Field Trials” has established a first description
of field trials and its phased approach. An iterative methodology to perform the tests was
presented, and a set of tests have been designed to validate the features that have been defined in
WP 1, “Architectural Framework” and the metrics associated with each test have been identified.
The second deliverable, D4.2, “Definition of Phase One Field Trials” has presented the
organization of the tests, with a special focus on the Phase I trial, that were implemented at
MCLab premises comprising all the integration activities and first series of tests. The impact of
field trials on exploitation plans has been presented.
Phase I field trial is an essential field trial whose importance has to do not only with the
verification of the correctness of the concept but also has to identify the enhancements that should
be introduced to be demonstrated in Phase II. This feedback is being continuously provided since
the involved partners are connected to this field trial testing their modules and correcting its
behaviours.
2 Objectives
The main objective of this deliverable is to present the first results of the tests that were specified
in deliverable D4.2, “Definition of Phase I Field Trials” [2]. These results are extremely
important since they will allow to obtain feedback from the integration of several modules
developed by several partners and this will allow that the TORRENT concept can be validated.
Other sub-objectives are:
o Verification of first functionalities of the LAP and RG, according with the tests defined
o Verification of integration of ADSL into the LAP
o Providing an analysis of the results and give some recommendations for phase II field
trials.