Facility planning for implementation 47
Flow rate and pressure capacity of chilled water plant input to the design of the facility feed line and
dedicated water loop pipe diameters
Material compatibility within piping system to minimize the potential for electrochemical corrosion, and
must be corrosion-resistant
Minimization of elbows and other restrictions that increase flow resistance
Insulation of piping to minimize risk of condensation and reduce incidental heating of supplied chilled
water
Availability of a floor drain or reclamation system to capture system condensation
Structural securing of piping to support weight of distribution network filled with water
Water quality management, including particulate filtration, treatment, and flushing provisions, with
isolation valves for service requirements
Availability and access to a data center leak detection system to monitor the infrastructure system for
leaks
Air vents installed at the highest point in the pipe system
Each MCS-200/100 has an air vent, but additional vents in the supply piping system must be
considered.
HP Water Hook-Up Kit
HP recommends using the MCS-200/100 Water Hook-up Option Kit BW971A, available on the HP website
(http://www.hp.com), to connect the MCS-200/100 to a facility chilled water system. Each kit includes the
hoses and accessories required for connecting the facility supply and return lines to the main inlet and outlet
connections of an MCS-200/100 unit and must be installed prior to the delivery of an MCS-200/100.
MCS-200/100 Water Hook-Up Option Kit contents
Item Description (quantity)
1
Main hose assembly* (2)
2
90-degree elbow assembly (2)
3
Teflon gasket (2)